New section 20 (4A)
insert
(4A) The planning and land authority may refuse to approve the application if—
(a) the applicant is required to provide the authority with a unit title assessment report under section 17 and—
(i) has not provided a unit title assessment report; or
(ii) has provided a unit title assessment report that is more than 3 months old; or
(b) the authority has asked for further information under section 22F and the applicant has not provided some or all of the information by—
(i) the end of the period stated in the request; or
(ii) if the authority has extended the period within which the further information must be provided—the end of that period.